Friday, April 9, 2010

FriDay

Hye guys...
Updating my blog with today`s activities...
What I am managed to observe today is about the slab installation...
Whenever the digging process had finished, they will do slab installation...
A 25 tonnes crane is used to carry the slab from its store place to the required area...
Once the slab is installed on the ground, they will do leveling to make sure the level between each other slab are the same...
But there is a problem today where the slab is not at the same level...
This will make the water cannot flow smoothly and for dry season, there will be a pond occurred because the flow cannot passes the higher slab because at the current state the flow is at the lower slab...So it need to be at the same level to make sure the flow will always continuous flowing...
So the site officer had discussed to put iron rod on the piles while the slab will laid down on the iron rod plus the slab...
One problem settled for today...